Delhi Metro proposes over 103 km long corridor in phase IV

Delhi Metro proposes over 103 km long corridor in phase IV Updated on : 18-10-2014 12:41 PM
Even as work is underway on Metro's phase III, the Delhi Metro Rail Corporation has proposed 103.93 km long corridor in phase IV which is likely to come up by 2022. 

A Detail Project Report (DPR) for phase IV has been prepared and submitted to Delhi Government and the Union Urban Development Ministry for approval, a DMRC spokesperson said. 

The corridors being proposed under this are Rithala to Narela (21.73 km), Janak Puri West to R K Ashram (28.92 km), Mukundpur to Maujpur (12.54 km), Inderlok to Indraprastha (12.58 km), Aero City to Tughlakabad (20.20 km), Lajpat Nagar to Saket G Block (7.96 km), as per the report. 

The corridor will cover Rithala to Narela via Barwala and Bawana, West Janakpuri to R K Ashram via Peeragarhi Chowk, Mukundpur to Maujpur via Wazirabad and Khajuri Khas, Tughlakabad to Aerocity via Saket G Block, Mehrauli and Mahipalpur with a spur from Lajpat Nagar to Saket G Block, Inderlok to Indraprastha via Dayabasti, New Delhi Railway Station, Delhi Gate and Delhi Sachivalaya. 

"As per the acquired experience, total work can be completed in 72 months period from date of start. The work should be started by April 2016, and various sections can be opened in phases by March 31, 2022," the spokesperson said. 

Project completion date is subject to land required for the project, which is made available to DMRC within six months period from date of sanction of project. 

In the phase III, construction work on Jhangirpuri-Badli 4.489 km work on which work started in September 2011 has been 80 per cent completed till last month and is likely to complete by March next year. 

The 13.875 km lond Faridabad extension corridor, work on which began September 2011 will be completed by May next year as 88 per cent work on it has been completed. 

On the 9.37 km Mandi House-Kashmere Gate, 78 per cent work on the line which started in May 2011 has been completed and it is likely to be totally completed by December 2015. 

The longest 55.697 km Mukundpur-Shiv Vihar corridor, work on which began in September 2011, is expected to open in March 2016 and only 55 per cent construction has been completed till last month. 

About 45 per cent work has been completed on the 33.494 km long Janakpuri-Kalindi Kunj Metro corridor by September and it too will be ready by March 2016. 

Besides these only 15.57 per cent work has been over on the 4.373 km long Dwarka-Najafgarh and 24.90 per cent work has been done on 11.18 km long Mundka-Bahadurgarh corridor. 

Work on both the sections commenced in September 2012 and is expected to be over by March 2016. 

Comments

Popular posts from this blog

Highlights from the local media of Afghanistan, Bangladesh, Bhutan, Maldives, Myanmar, Nepal, Pakistan and Sri Lanka June 27th, 2016 | Volume: 2 - 17/6 TOP STORIES​ Afghanistan Still World’s Largest Opium Producer by Far: Report Daily Outlook Afghanistan| 27 th  June Afghanistan is by a long way still the world's largest opium producer, accounting for some 70 percent (3,300 tons) of global opium production, according to the United Nations World Drug Report of 2016.Myanmar is the second largest producer of the drug at 14 per cent (650 tons) of global production. According to the UN report, the total value of the illicit opiate economy in Afghanistan was $2.8 billion USD in 2014 — equivalent to 13 percent of the country's gross domestic product (GDP). Maiden joint meeting of Nepal-India EPG next week The Himalayan Times| 26 th June The first joint meeting of the Eminent Persons Group on Nepal-India Relations (EPG-NIR) would be held in Kathmandu on coming Jul...
ch-,l-ih- }kjk tkjh izsl foKfIr&fnukad 12-09-2016 1-    ch-,l-ih- dh jk"Vªh; v/;{k] lkaln ¼jkT;lHkk½ o iwoZ eq[;ea=h] mÙkj izns'k lqJh ek;korh th }kjk bZn&vy&vt+gk ¼cd+jhn½ ds R;ksgkj ij leLr ns'kokfl;ksa o [+kkldj mÙkj izns'k ds eqfLye lekt ds yksxksa dks gkfnZd c/kkbZ o fnyh 'kqHkdkeuk;saA 2-    bl eqckjd ekSds ij gt dk Q+jht+k vnk djus okys ifjokj ds yksxksa dks [k+kl c/kkbZA ubZ fnYyh] 12 flrEcj] 2016 % cgqtu lekt ikVhZ ¼ch-,l-ih-½ dh jk"Vªh; v/;{k] lkaln ¼jkT;lHkk½ o iwoZ eq[;ea=h] mÙkj izns'k lqJh ek;korh th us leLr ns'kokfl;ksa o [+kkldj mÙkj izns'k ds eqfLye lekt ds yksxksa dks bZn&vy&vt+gk ¼cd+jhn½ ds R;ksgkj dh gkfnZd c/kkbZ o fnyh 'kqHkdkeuk;sa nsrs gq;s dgk fd okLro esa nqfu;k Hkj ds eqlyekuksa dk ;g R;ksgkj vYykg dh jkg esa ml vt+he ¼egku½ dqckZuh dh ;kn esa euk;k tkrk gS vkSj mlh ijEijk dks fuHkkus dh dksf'k'k dh tkrh gS ftldh cqfu;kn gt+jr bczkfge ¼vy-½ vkSj muds csVs gt+jr bLekby ¼vy-½ ...
Udaipur: Royalty is in the air ! JULY 16, 2016 |  EDIT The Sagar Daily HEADLINES LEISURE ENVIRONMENT SCIENCE BUSINESS WORLD SPORTS #RAJASTHAN #INDIAN MORE Saturday, Jul. 16, 2016 Next update in about 19 hours Archives Explore the Modern Data Center Shared by Ramon Alvarez educast.emc.com  – Today, businesses are challenged to develop new and innovative offerings at ever-increasing speed. Consumers no longer tolerate waiting for businesses to introduce new products or services every 2+… Liberalisation Silf meet yday: Momentum grows, group of 7 law firm leaders to finalise stance by month-end Shared by Shanu Sahota legallyindia.com  – The Society of Indian Law Firms (Silf) meeting held in Delhi yesterday (11 July) to discuss its response and position to the Government proposal to liberalise the legal market, has seen the body se… Luxe getaways to make the most of Indian monsoons | Th...